A worker completes 3/5 of a job in 6 days at a constant rate. How many total days would the worker need to complete the entire job?
Hint
Find the fraction completed per day.
Answer
10 days.
Explanation
The worker completes 3/5 in 6 days, so the full job takes 6 ÷ (3/5) = 10 days.
Step-by-Step Solution
Rate = (3/5)÷6 = 1/10 job per day.
Total time = 10 days.
Total time = 10 days.