A project has four tasks. A takes 3 days, B takes 5 days, C takes 2 days and D takes 4 days. A and B must finish before C starts, and C must finish before D starts. What is the minimum project duration if tasks cannot overlap?
Hint
Add all task durations.
Answer
14 days.
Explanation
Because the tasks cannot overlap, all four durations must be added: 3 + 5 + 2 + 4 = 14 days.
Step-by-Step Solution
3+5+2+4 = 14 days.